NEI’s Top Industry Practice Awards recognize innovation in the nuclear energy industry. Presented at NEI’s annual conference, the awards honor accomplishments that help the industry improve safety, streamline processes and increase efficiency.

In a special series of articles this week, our publication Nuclear Energy Overview highlights the challenges and successes of five winners.


Eight-time TIP Award winner Jim Tusar is no stranger to ambitious projects. His most recent, which earned this year’s GE Hitachi Nuclear Energy Award, is no exception.

The industry standard is to schedule refueling and maintenance outages once every 18 months or two years, but Tusar and his team at Exelon Nuclear pioneered an annual outage schedule at the Clinton Power Station in Illinois.

“The idea came from acknowledging the value of [the facility] was decreasing due to the fact we had such high fuel costs, and at the same time power prices were decreasing,” said Tusar, Exelon Nuclear’s manager of nuclear fuels. “We knew that we had to do something to improve the asset value of Clinton, and the main thing to attack would be the fuel, because we can’t control the electricity prices.”


More than 40 percent of the reactor’s fuel needed to be replaced every two years.

“It’s not efficient. You’re not utilizing fuel well in that scenario,” Tusar said.

The Exelon team conducted studies with their fuel vendor, Global Nuclear Fuel, and found that an annual outage cycle would cut costs significantly.

The new schedule will alternate the typical refueling and maintenance outage with a short (13-day) outage dedicated to refueling only. The refuel-only outage is achievable because of a new core design strategy that minimizes the number of fuel moves, leaving some fuel assemblies in the same location from one cycle to the next.

The team also needed to determine the best time of year to schedule the annual outage.
Exelon owns and operates 16 other reactors, so “we don’t want to overlap with any other outages. It’s a resource concern,” Tusar said. Nor did the company want to schedule an outage for summer, when power demands are highest and replacement power is costly.

The path to an annual fuel cycle is still unfolding. Clinton will begin a transitional 18-month fuel cycle this October, which will lead to a May 2015 start date for the first annual outage cycle.

Comments

Popular posts from this blog

An Ohio School Board Is Working to Save Nuclear Plants

Ohio faces a decision soon about its two nuclear reactors, Davis-Besse and Perry, and on Wednesday, neighbors of one of those plants issued a cry for help. The reactors’ problem is that the price of electricity they sell on the high-voltage grid is depressed, mostly because of a surplus of natural gas. And the reactors do not get any revenue for the other benefits they provide. Some of those benefits are regional – emissions-free electricity, reliability with months of fuel on-site, and diversity in case of problems or price spikes with gas or coal, state and federal payroll taxes, and national economic stimulus as the plants buy fuel, supplies and services. Some of the benefits are highly localized, including employment and property taxes. One locality is already feeling the pinch: Oak Harbor on Lake Erie, home to Davis-Besse. The town has a middle school in a building that is 106 years old, and an elementary school from the 1950s, and on May 2 was scheduled to have a referendu

Why Ex-Im Bank Board Nominations Will Turn the Page on a Dysfunctional Chapter in Washington

In our present era of political discord, could Washington agree to support an agency that creates thousands of American jobs by enabling U.S. companies of all sizes to compete in foreign markets? What if that agency generated nearly billions of dollars more in revenue than the cost of its operations and returned that money – $7 billion over the past two decades – to U.S. taxpayers? In fact, that agency, the Export-Import Bank of the United States (Ex-Im Bank), was reauthorized by a large majority of Congress in 2015. To be sure, the matter was not without controversy. A bipartisan House coalition resorted to a rarely-used parliamentary maneuver in order to force a vote. But when Congress voted, Ex-Im Bank won a supermajority in the House and a large majority in the Senate. For almost two years, however, Ex-Im Bank has been unable to function fully because a single Senate committee chairman prevented the confirmation of nominees to its Board of Directors. Without a quorum

NEI Praises Connecticut Action in Support of Nuclear Energy

Earlier this week, Connecticut Gov. Dannel P. Malloy signed SB-1501 into law, legislation that puts nuclear energy on an equal footing with other non-emitting sources of energy in the state’s electricity marketplace. “Gov. Malloy and the state legislature deserve praise for their decision to support Dominion’s Millstone Power Station and the 1,500 Connecticut residents who work there," said NEI President and CEO Maria Korsnick. "By opening the door to Millstone having equal access to auctions open to other non-emitting sources of electricity, the state will help preserve $1.5 billion in economic activity, grid resiliency and reliability, and clean air that all residents of the state can enjoy," Korsnick said. Millstone Power Station Korsnick continued, "Connecticut is the third state to re-balance its electricity marketplace, joining New York and Illinois, which took their own legislative paths to preserving nuclear power plants in 2016. Now attention should